Board and Batten Installation Instructions

Starting the installation

The siding must be installed over furring strips to allow for airflow and enable drainage for excess moisture. A ¾-inch (19 mm) unobstructed ventilation duct must be left between the siding and the building; please refer to local building codes to verify ventilation duct guidelines and other building requirements.

board and batten installation instruction douple furring

During installation, create ventilation space behind the siding by using double furrings. Install the first vertical furring strips directly to the frame of the building, then apply a horizontal furring strips on top of the vertical ones following the guidelines below:

Do not install the furring strips diagonally as this will impede ventilation and prevent water from draining freely.

The siding should not touch the ground or other horizontal surfaces and cannot be closer than 8 inches (203 mm) from the ground.

You should also…

board and batten installation instructionPainting Guidelines

Siparila board and batten siding is a high-quality exterior siding that comes primed on all four sides. The primer protects the wood during the installation process and provides a good base for the two top coats required to seal the wood. When painting, please sure all exposed wood and nail heads are painted to retain the integrity of the finish.

Board and batten installation

PDF – Download Board and Batten Installation Instruction

PDF – Download Siparila Siding Brochure



Share on FacebookTweet about this on Twitter